The foundation and retaining structure works at SCM01 have been completed, Smart City Malta has said.

The company was engaged in the construction of the super-structure. Aligned with this structural progress, the façade works have also started under the appointed local contractor.

SCM01 is the first Smart City building in Phase One currently under construction. It will consist of 12,000 square metres of ready-to-use Grade A offices to be completed and handed over to the first business partners by 2010, as scheduled, the company said.

Smart City Malta has submitted its application for the site-wide grading permit for all phases of the self-sustained business township which will cover the lagoon, shopping boulevard and the residential area to the Malta Environment and Planning Authority. The tender for the site-wide grading has also been issued and grading works are expected to commence shortly.

Sign up to our free newsletters

Get the best updates straight to your inbox:
Please select at least one mailing list.

You can unsubscribe at any time by clicking the link in the footer of our emails. We use Mailchimp as our marketing platform. By subscribing, you acknowledge that your information will be transferred to Mailchimp for processing.