Works on the interconnector project are advancing according to plan and horizontal directional drilling (HDD) is expected to start in the coming days at Qalet Marku bay.

Enemalta said the HDD operation will be performed by a drill machine placed on land in an area dedicated for the plant and ancillary equipment. Pilot hole drilling will be performed by pushing a drill head connected to a hollow high density polyethylenepipe, into the ground at a small angle from land towards the sea. Sections of mountable drilling rods are added and pushed following a defined path.

A culvert will be on the land’s side, from the substation and down to the landfall by the sea.

Horizontal directional drilling shall be performed for an approximately 213m long HDPE pipe from the end of the culvert and out to sea.

The subsea exit point for the drilling will be at 4.5 meters water depth, some 106 meters from shore. A barge will then be positioned outside the exit point for assistance during the pilot drilling and reaming operation.

During installation, the submarine cable will be pulled through the HDPE pipe and up to the substation.

The reason for horizontal directional drilling instead of conventional trenching is to reduce the environmental impact at the landfall, both on the beach and at sea.

Apart from being an environmentally sensitive technique, which does not affect marine life, this method will also ensure no disruption to traffic along the Coast Road, Enemalta said.

 

Sign up to our free newsletters

Get the best updates straight to your inbox:
Please select at least one mailing list.

You can unsubscribe at any time by clicking the link in the footer of our emails. We use Mailchimp as our marketing platform. By subscribing, you acknowledge that your information will be transferred to Mailchimp for processing.