Advert

Work well underway on tunnel for interconnector cable

Video: Mark Zammit Cordina

Work is well under way on a 4km tunnel from Maghtab to Kappara distribution centre, which will host the cable linking Malta's power network with that of Sicily.

Prime Minister Lawrence Gonzi this morning visited the project, which is being handled by Polidano Brothers.

Some 650 metres of the tunnel have so far been dug. On a good day, depending on the sort of rock found, some 25 metres are dug, Dr Gonzi was told.

During his visit, Dr Gonzi attended Mass on site to mark the feast of St Barbara, patron saint of miners.

The tunnel is expected to be completed within a year.

Advert

2 Comments

Post comment

Please see our new Comments Policy

Comments are submitted under the express understanding and condition that the editor may, and is authorised to, disclose any/all of the above personal information to any person or entity requesting the information for the purposes of legal action on grounds that such person or entity is aggrieved by any comment so submitted.

At this time your comment will not be displayed immediately upon posting. Please allow some time for your comment to be moderated before it is displayed.

For more details please see our Comments Policy

Your User Profile is incomplete.
Please click here to complete your profile before posting comments.

Mario Busuttil

Dec 5th 2012, 06:44

Mhux kull kuntrattur ghandu dik it tip ta ghodda biex thaffer mini taht l art......ghalhekk it tender hada Polidano....

Advert
Advert