Advert

Wind farms: Data collection at Mellieha to continue for two more years

An artist's impression of the proposed wind farm.

An artist's impression of the proposed wind farm.

Mepa has granted a two-year extension for the operation of a data-gathering mast at l-Ahrax in Mellieha for studies on the site's suitability for an offshore wind farm.

The extension had been sought by scientists. The projected wind farmm at  Sikka l-Bajda  will provide electricity for some 40,000 households.

Another two years of collecting data would reduce the margin of error when extrapolating the results to cover the 20-year wind farm lifetime.

Tonio Sant, director of the University’s Institute for Sustainable Energy, which is overseeing the collection, correlation and analysis of the data collected by the Malta Resources Authority, said earlier this year that data compilation in conjunction with the required studies would reaffirm what had already been established – that the 11-square-kilometre Sikka l-Bajda is a good location for an offshore wind farm.

Wind studies at L-Aħrax Point began in November 2009 after the 80-metre wind mast was installed. The data being collected from the mast is being correlated to the wind data that has been collected since 1997 from the institute’s wind station at Wied Rini, near Baħrija.

“Statistical correlation, like any experimental technique, has a margin of error, especially when you are extrapolating the data to cover a 20-year period. A longer measurement period would help decrease that margin of error,” Dr Sant told The Sunday Times.

Around 19 to 24 wind turbines, each with a diameter of between 100 and 126 metres, are expected to be installed at Sikka l-Bajda, a reef covering an area of 11 square kilometres, situated around two kilometres to the east of L-Aħrax tal-Mellieħa.

According to studies based on wind data collected so far, these would generate around 200 gigawatt-hours (Gwh) of electricity – which is about 10 per cent of what Enemalta produces every year, and the annual electricity consumtion of around 40,000 households.

Constructing an offshore wind farm is a lengthy process. A look at similar projects abroad show that a wind farm takes between six and eight years to construct, including time for studies and commissioning.

The Malta project, estimated to cost around €300 million, is expect­ed to be in place by 2016, four years before EU countries must generate 10 per cent of their energy through renewable sources. The wind farm alone would cover just over three per cent of this target.

This project forms part of the National Renewable Energy Action Plan, which aims to generate electricity not only from wind but also from the sun.

Dr Sant said studies were continuing on the environmental impact of the project and the suitability of the site.

These studies, overseen by the Resources Ministry, are costing the government around €300,000 and are expected to be concluded in about a year’s time.

Engineer Robert Farrugia, also from the University’s Institute for Sustainable Energy, said the institute had been collecting wind data from its station at Wied Rini since 1997, taking measurements of wind speeds at 10, 23 and 45 metres. This station is 220 metres above sea level while the one at L-Aħrax is just 15 metres above sea level.

Dr Sant said the environmental assessments included geological studies on the seabed to determine whether the rock was strong enough to anchor turbines.

According to preliminary investigations, it appeared that the seabed was suitable, despite the presence of underwater caves.

Once these studies are completed, the developer will conduct further geo-technical studies on what kind of foundations the turbines require. The foundations alone are estimated to cost about 20 per cent of the total cost of the project.

The bigger the diameter of the turbines chosen, the slower the rotational speed of the blades, which would have a positive effect on aesthetics.

The high-tech designs of today’s turbines have resulted in much less noise.

Dr Sant said technology was improving drastically with modern turbines estimated to generate between 25 and 35 per cent more energy per year.

“These are more expensive but they give a better yield and would eventually result in a lower cost of energy,” Dr Sant said.

Studies conducted include:

• Effect of wind farm on birds and bats;
• Effect on marine ecology;
• Visual and noise impact;
• The impact of the rotating shadow of the turbines;
• The impact on the quality of the marine environment, including any possible pollution;
• Study on the possible archaeological remains;
• Impact on air traffic;
• Effect on communications, including mobile coverage;
• Impact on fishing and aquaculture.

Advert

39 Comments

Post comment

Comments are submitted under the express understanding and condition that the editor may, and is authorised to, disclose any/all of the above personal information to any person or entity requesting the information for the purposes of legal action on grounds that such person or entity is aggrieved by any comment so submitted.

At this time your comment will not be displayed immediately upon posting. Please allow some time for your comment to be moderated before it is displayed.

Your User Profile is incomplete.
Please click here to complete your profile before posting comments.

Michael Pule

Nov 18th 2011, 13:53

Ms Muscat, you seem to be a qualified expert on alternative energy. Come on, give us your proposals then, please....

M.O. Micallef

Nov 18th 2011, 21:16

Very sorry Mr Pule, Ms Muscat is an expert about evrything on the planet....emmm sorry in the universe...so Mr Pule next time round before stating your reply check you facts

G G Debono

Nov 18th 2011, 10:54

Mr Galea

You think they are ugly. Most people think they are fine - because they represent a new clean way to produce energy. ( most surveys show that approx 5% of people hate them. 15% are neutral and 80% are positive)

Also, the average working life of a turbine is 25 years (not 50 years) - and they can be removed without leaving a trace.

So presumably you are one of the 5% who make a lot of noise but are in fact a small minority.

The way to go for Malta would have been start on land on land - it is 2/3 cheaper etc - going straight to offshore is positively gimmicky and not the way to start, (see my comment below - Yesterday, 13:58)

J. Debono

Nov 17th 2011, 15:26

To produce 200GWH by photovoltaics, you have to cover a substantial area, ll of which is private.

Besides being more expensive than wind turbines, it does not produce electricity at night and cloudy days.

The cheaper and much more efficient solar water heaters should be first introduced, THEN photovoltaics, as they're still extremely expensive and very inefficient (less than 16%), as opposed to solar water heater (60% efficiency and cheaper materials).

In order to produce enough electricity by PVP to heat water, you have to invest almost double the amount in PVP than solar water heater (obviously excluding any grants).

Mr Jurgen Grech

Nov 17th 2011, 17:03

@J Debono...the idea is not to become fully reliant on PVP! Renewable energy sources need to work together...so I agree with you that together with PVP, there is a need for more solar water heaters as well...however i'm sure that if we were to cover most public buildings in PVP and they were given for free to anyone willing to install one on his roof, even at 16% efficiency, we would lower demand on Enemalta by a long stretch!!

J. Debono

Nov 17th 2011, 19:18

@ Mr. Grech

With less than 2,000 Euros, I installed a solar water heater, changed all my bulbs to energy savers, and did double glazing instead of single glazing (the difference in price I calculated).

The result - 7 Units less consumption per day. App. 4-5Units from solar water heater, 1-2 Units from bulbs, 0.5 - 1 Unit ftom insulation.

To produce 7 Units per day with PVP - the cost is app. 5,000 - 6,000Euro.

They are currently too expensive

Mr Jurgen Grech

Nov 17th 2011, 14:00

It is also possible in areas which are igneous in nature not sedimentary! Malta is a sedimentary island...geothermal is not an option unfortunately.

V. Cauchi

Nov 17th 2011, 15:18

@ Mr Jurgen Grech

Best read on drilling in sedimentary rock http://www.greenrock.com.au/geothermalProcess.php

Mr Jurgen Grech

Nov 17th 2011, 17:00

It is easier to drill, agreed, but you would have to go deeper and deeper in order to get to those areas which are hot enough to boil water...in countries like Iceland and certain parts of Italy, hot magma is much closer to the surface and makes geothermal plant much more convenient to install...geothermal energy could however be an option for cooling/heating as it is currently being investigated in the new parliament building.

V. Cauchi

Nov 17th 2011, 18:15

No problem digging deeper or looking for new technology producing very hot water which could then be brought to the boil by CSP (concentrated solar power) over a very limited area, given our limitations. What is needed is inventiveness and lateral thinking, local government initiative and private entrepreneurship to get ideas rolling. I am sure some foreign entrepeneur will come with pretty good ideas if only we advertise our needs thoroughly.

Jonathan Scerri

Nov 17th 2011, 12:55

Such an investment would have to be seen in virtue of its life cycle costs, not just the capital cost. It's about time this country stops demonishing renewable energy if it ever wants to diversify its energy sources and reduce dependency on fossil fuels.

B Ellul

Nov 17th 2011, 13:18

Since you have already concluded that the project is not viable, I would suggest that you contact the ministry and explain.... a cheap consultant (or shall I say economic professor) is always welcome! AND other countries who already/will be investing in wind technologies should also contact you as well.... not to commit all the same mistake.... u mur l'hemm....

G G Debono

Nov 17th 2011, 14:01

Another good reason for starting on land - land based wind energy provides energy at about the same price(or cheaper ) than offshore ---- the infrastructure costs about one half or even one third to build AND maintain.

But our ministry of silly decisions turned the original land based project down.

G G Debono

Nov 17th 2011, 16:36

Sorry - correction - - -

what I meant to write is:

G G Debono
Today, 14:01
Another good reason for starting on land - land based wind energy provides energy at about the same price(or cheaper ) than FOSSIL FUEL (delete 'offshore ' ) ---- the infrastructure costs about one half or even one third to build AND maintain THAN OFFSHORE .

But our ministry of silly decisions turned the original land based project down.

B Ellul

Nov 17th 2011, 13:20

if you're worrying about navigation.... well buy a small boat and anchor yourself next to the turbine to signal other ships.... have you heard of the word RADAR!

G G Debono

Nov 17th 2011, 14:02

Should be ok with safe navigators - as long as they go easy with the gin-and-tonic ?

J. Debono

Nov 17th 2011, 14:51

well, in my opinion a 126METRE blade is easily visible!!

John Borg

Nov 17th 2011, 12:59

wasted 10 years? renewable energy is still in an experimental stage. people who bought panels for their homes just three years ago paid a higher price than was is being paid now for panels that produce less output. It does not pay to rush into so called clean systems which cost much more. 300 million for so few households is not a good return whichever way one looks at it.

Edward Mallia

Nov 17th 2011, 14:25

I suggest that request for another two years of wind speed data has little or nothing to do with extrapolating one year's data over the next twenty years. This extrapolation over however many years is not usually part of the procedure in determining the search wind farm sites. The German firm once interested in a land-based farm at Marfa may have had no more than six months of measurements. And wind farms in the North sea DO NOT take 6 to 8 years from start to finish. North Rhyl offshore of North Wales took less than 4 years.
In any case, if a lack of long time base measurements are really what's holding up Sikka l-Bajda, what does one make of Ing. Robert Farrugia's statement that 'the institute has been collecting wind data from its station at Wied Rini since 1997, at 10, 23 and 45m [above ground level]'? Was not Bahrija (Wied Rini) the second of the three farm sites in Minister Pullicino's proposals? How come we do not have one miserable turbine up there? Or is the Institute for Sustainable Energy misinforming the public about Bahrija?

joe vella

Nov 17th 2011, 12:30

there are very few windless days in malta, dead calm days are few and far between
and the location being reviewed is well exposed to the predominant winds in malta
one hopes that we do not end up with never ending studies and the project takes an eternity to materialise, that is if it eventually materialises!

Michael Borg

Nov 17th 2011, 12:30

Whilst your points are valid, there are aspects of the present power stations that must be taken into account when assessing the viability of wind turbines and other renewable technologies.

As you pointed out, wind turbines do not continously operate at their rated capacity (but still reach it above certain wind speeds). In fact offshore wind turbines have a load factor of around 35-40% (that is, on average they operate at rated capacity for 35-40% of a given time period). The present power stations do not run at 100% capacity as one would think, due to the electric grid fluctuations, although they have a much higher load factor.

Another factors to be considered are the security of supply, with oil prices continously changing, the price of electricity (and water in Malta's case due to the heavy reliance on reverse osmosis) will also fluctuate. With wind turbines and other renewable technologies, once the capital investment, operational lifetime, and maintenance costs are established, a fixed price for electricity is used.

Also with the introduction of the carbon dioxide emissions tax by the European Commission, the price of electricity generated by using fossil fuels will be more expensive.

This is by no means an exhaustive analysis of the situation, but one must try to take a full view to appreciate the implementation fo renewable energies to substitute our current addiction to fossil fuels.

Advert
Advert