Smart City foundations completed

The foundation and retaining structure works at SCM01 have been completed, Smart City Malta has said.

The company was engaged in the construction of the super-structure. Aligned with this structural progress, the façade works have also started under the appointed local contractor.

SCM01 is the first Smart City building in Phase One currently under construction. It will consist of 12,000 square metres of ready-to-use Grade A offices to be completed and handed over to the first business partners by 2010, as scheduled, the company said.

Smart City Malta has submitted its application for the site-wide grading permit for all phases of the self-sustained business township which will cover the lagoon, shopping boulevard and the residential area to the Malta Environment and Planning Authority. The tender for the site-wide grading has also been issued and grading works are expected to commence shortly.

Advert

0 Comments

Post comment

Comments are submitted under the express understanding and condition that the editor may, and is authorised to, disclose any/all of the above personal information to any person or entity requesting the information for the purposes of legal action on grounds that such person or entity is aggrieved by any comment so submitted.

At this time your comment will not be displayed immediately upon posting. Please allow some time for your comment to be moderated before it is displayed.

Your User Profile is incomplete.
Please click here to complete your profile before posting comments.

Advert
Advert