Nasa delays shuttle launch by at least a week

Nasa delayed its first shuttle launch of the year for at least a week to allow time for engineers to review a potential problem with valves that keep the fuel tank pressurised, according to managers.

The shuttle Discovery and seven astronauts had been scheduled to launch on February 12 to deliver a final set of solar wing panels to the International Space Station.

The mission was postponed until at least February 19 due to an issue with the valves that keep hydrogen fuel properly pressurised for the shuttle's three main engines.

"For the main engines to run correctly, the hydrogen tank has to be properly pressurised," said shuttle programme manager John Shannon.

During Nasa's last shuttle flight in November, a tiny piece of one valve broke off. That posed no threat to the shuttle but Nasa wants more time to consider what would happen if a bigger piece of the valve's lip breaks off or if a similar event were to occur at a different time during liftoff.

"We want to make sure we got this right," Dr Shannon said. "This has important consequences for us."

Advert

0 Comments

Post comment

Comments are submitted under the express understanding and condition that the editor may, and is authorised to, disclose any/all of the above personal information to any person or entity requesting the information for the purposes of legal action on grounds that such person or entity is aggrieved by any comment so submitted.

At this time your comment will not be displayed immediately upon posting. Please allow some time for your comment to be moderated before it is displayed.

Your User Profile is incomplete.
Please click here to complete your profile before posting comments.

Advert
Advert